Free trade sequencing planner

Who do you book, and when?

Renovations don't blow out because trades are slow. They blow out because the order is wrong: the screen measured before the tiles, the cabinets ordered late, the membrane rushed. Here is the correct sequence, how long each stage takes, and how far ahead each trade books out.

Room

The trap room. Waterproofing must cure before tiles, the screen is measured after tiles, and every trade comes back twice (rough-in, then fit-off).

1523days of trades on site
58weeks start to done, waits included
6 wksahead you should start booking

The sequence

  1. Demolition & strip-out

    1–2 days
    book 2 wks ahead

    Rubbish off site, old membrane out. If the house is pre-1990, allow for an asbestos check first.

  2. Plumber, rough-in

    1–2 days
    book 4 wks ahead

    All pipe moves happen now. Moving a drainage point later is the most expensive variation on the job.

  3. Electrician, rough-in

    1 day
    book 3 wks ahead

    Lighting, fan, heated towel rail circuits in the wall while it's open.

  4. Carpenter, sheeting & niche

    1–2 days
    book 3 wks ahead

    Villaboard, niche framing, wall-hung vanity blocking. Decide the niche NOW, not at tiling.

  5. Waterproofing

    2–4 days
    book 2 wks ahead

    AS 3740 membrane, two coats, each needs cure time. Rushing this is how bathrooms fail. Days shown include cure.

  6. Tiling

    4–6 days
    book 6 wks aheadorder tiles: 3 wk lead

    Good tilers book out furthest of any trade. Tiles on site BEFORE the tiler arrives.

  7. Grout, silicone & clean

    1 day

    Usually the tiler's last day.

  8. Shower screen measure

    book 3 wks aheadorder screen (made to order): 2 wk lead

    Can only be measured AFTER tiling. The made-to-order wait starts here; this is the classic dead fortnight nobody plans for.

  9. Plumber, fit-off

    1 day

    Toilet, vanity, tapware, shower set. Same plumber as rough-in; book both visits together.

  10. Electrician, fit-off

    1 day

    Lights, fan, accessories. Book with the rough-in.

  11. Painter

    1–2 days
    book 2 wks ahead

    Ceiling and untiled walls. Wet-area paint only.

  12. Glazier, screen install

    1 day

    Lands when the made-to-order screen arrives. Silicone cures overnight before first use.

Where the weeks go missing

Know what you're building before you book anyone.

One photo of your room comes back finished, with every product priced, quantified and linked to the supplier. Hand that schedule to your trades and the quotes come back tight.

Durations and lead times are typical 2026 Australian bands for a standard single-room renovation, drawn from the TuttoCasa costing engine's trade scopes. Your trades, your suburb and your site set the real calendar; use this as the shape of the job, not a contract program.